What’s been going on

Steel decking has now been installed to Section 1 of the new building, and foundations completed to allow steel erection to progress on Section 2 next week. Read more

Hollingworth BSF Bulletin 13/05/2010

What’s been going on

Steelwork is now complete to the first wing of the new building. Next week we will be placing the deck sheets to this wing to form the soffit to the 1st and 2nd floor slabs. Read more

Hollingworth BSF Bulletin 06/05/2010

What’s been going on.

You will have probably noticed real changes at the back of the College this week as we have started erection of the steel frame to the new building. The first section to be erected is the wing containing the MFL, Learning support, Music, English and Maths classrooms. This section also includes the lift that gives access to all levels within the new building. Read more

Hollingworth BSF Bulletin 28/04/2010

What’s been going on

Foundations continue to the central wing of the new College building. All the old foundations to the LRC/English block have now been removed to allow the new foundations to be constructed within the footprint of the LRC building. Read more